Next stage completed

Just eight months after the groundbreaking, the topping-out ceremony for the expansion marks an important milestone for this major project, with an investment of 25 million euros. The construction work is fully on schedule and within budget. Since the start of the project, the foundation has been laid, exterior and interior walls have been built, the steel substructure for the roof has been completed, and the window fronts have been installed. The facility is expected to be operational by the end of May 2025.